STRUCTURE:
H/R and LMR brick work in progress.
A1 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work completed
A2 FLAT:
kitchen PF rcc work completed.
plumbing wall chasing work completed
A3 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work completed.
B1 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing work completed.
B2 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing... moreSTRUCTURE:
H/R and LMR brick work in progress.
A1 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work completed
A2 FLAT:
kitchen PF rcc work completed.
plumbing wall chasing work completed
A3 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work completed.
B1 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing work completed.
B2 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing work completed.
B3 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing work completed.
B4 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
Next we have planned plumbing work.
C1 FLAT:
Inner wall plastering work completed.
Next we have planned plumbing work.
C2 FLAT:
Inner wall plastering work completed.
Next we have planned plumbing work.
C3 FLAT:
Inner wall plastering work completed.
Next we have planned plumbing work.
Common:
parapet wall and column RCC work in progress.
Staircase and lobby area plastering works in progress
Stilt area plastering works in progress