B1 FLAT:
Toilet wall and floor, General floor tiles work in progress - 95% completed
Kitchen pf granite work completed
Shelf work in progress
Inner wall putty and ceiling white wash completed.

B2 FLAT:
Inner wall 1st coat putty and ceiling white wash work completed
Kitchen pf granite work completed
Next we have planned tiles work.
Next we have planned shelf work

B3 FLAT:
Inner wall 1st coat putty work and ceiling white wash work completed
kitchen pf granite work completed
Shelf work...  more