B1 FLAT:
Toilet wall and floor, General floor tiles work in progress.
Kitchen pf granite work in progress.
Shelf work in progress
Inner wall putty and ceiling white wash completed.
B2 FLAT:
Inner wall 1st coat putty and ceiling white wash work completed
Kitchen pf granite work in progress.
Next we have planned tiles work.
Next we have planned shelf work
B3 FLAT:
Inner wall 1st coat putty work and ceiling white wash work completed
kitchen pf granite work in progress.
Shelf work in p... moreB1 FLAT:
Toilet wall and floor, General floor tiles work in progress.
Kitchen pf granite work in progress.
Shelf work in progress
Inner wall putty and ceiling white wash completed.
B2 FLAT:
Inner wall 1st coat putty and ceiling white wash work completed
Kitchen pf granite work in progress.
Next we have planned tiles work.
Next we have planned shelf work
B3 FLAT:
Inner wall 1st coat putty work and ceiling white wash work completed
kitchen pf granite work in progress.
Shelf work in progress
next we have planned tiles work.
A1 FLAT
Shelf work completed.
tiles 90% work completed.
kitchen pf granite work in progress.
next we have planned putty work.
A2 FLAT.
toilet wall and floor tiles progress.
kitchen pf granite work in progress.
Next we have planned putty work.
Next we have planned shelf work
A3 FLAT
Shelf work progress
kitchen pf granite work in progress.
next we have planned putty work.
next we have planned tiles work.
C1 FLAT:
inner wall putty work and ceiling white wash completed
kitchen pf granite work in progress.
Shelf work in progress
tiles work in progress
C2 FLAT:
tiles 90% work completed.
inner wall putty and ceiling white wash work completed
kitchen pf granite work in progress.
COMMON:
Water tank base slab structural work in progress.
H/R, LMR - Plastering work in progress.
OUTER:
Outer plastering work completed.
Outer plumbing work completed.
Next we have planned parapet area plumbing works