B1 FLAT:
toilet wall and floor tiles progress.
kitchen pf granite work in progress.
Shelf work in progress
inner wall and ceiling putty work progress.
B2 FLAT:
inner wall and ceiling 1st coat putty work completed
kitchen pf granite work in progress.
next we have planned tiles work.
Next we have planned shelf work
B3 FLAT:
inner wall and ceiling 1st coat putty work completed
kitchen pf granite work in progress.
Shelf work in progress
next we have planned tiles work.
A1 FLAT
Shelf ... moreB1 FLAT:
toilet wall and floor tiles progress.
kitchen pf granite work in progress.
Shelf work in progress
inner wall and ceiling putty work progress.
B2 FLAT:
inner wall and ceiling 1st coat putty work completed
kitchen pf granite work in progress.
next we have planned tiles work.
Next we have planned shelf work
B3 FLAT:
inner wall and ceiling 1st coat putty work completed
kitchen pf granite work in progress.
Shelf work in progress
next we have planned tiles work.
A1 FLAT
Shelf work completed.
tiles 90% work completed.
kitchen pf granite work in progress.
next we have planned putty work.
A2 FLAT.
toilet wall and floor tiles progress.
kitchen pf granite work in progress.
Next we have planned putty work.
Next we have planned shelf work
A3 FLAT
Shelf work progress
kitchen pf granite work in progress.
next we have planned putty work.
next we have planned tiles work.
C1 FLAT:
inner wall and ceiling putty completed
kitchen pf granite work in progress.
Next we have planned shelf work
next we have planned tiles work.
C2 FLAT:
tiles 90% work completed.
inner wall and ceiling putty work completed
kitchen pf granite work in progress.
COMMON:
Water tank base slab structural work in progress.
H/R, LMR - Plastering work in progress.
OUTER:
Outer plastering work completed.
Outer plumbing work completed.