B1 FLAT:
toilet wall and floor tiles progress.
kitchen pf granite work in progress.
Shelf work in progress
inner wall and ceiling putty work progress.

B2 FLAT:
inner wall and ceiling 1st coat putty work completed
kitchen pf granite work in progress.
next we have planned tiles work.
Next we have planned shelf work

B3 FLAT:
inner wall and ceiling 1st coat putty work completed
kitchen pf granite work in progress.
Shelf work in progress
next we have planned tiles work.

A1 FLAT
Shelf ...  more