STRUCTURE:
H/R brick work in progress.

A1 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work in progress.

A2 FLAT:
kitchen PF rcc work completed.
plumbing wall chasing work in progress.

A3 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work in progress.

B1 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
Next we have planned plumbing work.

B2 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
Next we have planned ...  more