B1 FLAT:
toilet wall and floor tiles progress.
kitchen pf granite work in progress.
Shelf work in progress
Next we have planned putty work.

B2 FLAT:
inner wall 1st coat putty work in progress.
kitchen pf granite work in progress.
next we have planned tiles work.
Next we have planned shelf work

B3 FLAT:
inner wall and ceiling 1st coat putty work completed.
kitchen pf granite work in progress.
Shelf work in progress
next we have planned tiles work.

A1 FLAT
Shelf work completed.
t...  more