1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.

B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.

B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc compl...  more