1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc compl... more1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
A1 FLAT
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
A2 FLAT.
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
A3 FLAT
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
C1 FLAT:
Inner plastering work completed.
Inner wall plumbing work completed.
toilet water proofing work completed
kitchen pf rcc completed.
Dead motor chipping work in progress.
Inner wall and ceiling 1st coat putty work in progress.
Next we have planned shelf work.
C2 FLAT:
Inner plastering work completed.
Inner wall plumbing work completed.
toilet water proofing work completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Inner wall and ceiling 1st coat putty work completed.
tiles work in progress
COMMON:
common area plastering completed.
Terrace LMR bottom RCC Work completed.
terrace H/R and LMR slab rcc work completed.
Next we have planned oht work.
carparking plastering work completed.
OUTER:
Outer plastering work completed.
Outer plumbing work completed.
Elevation Civil work completed.