STRUCTURE:
3rd floor RCC work is completed.
Next, we have planned to start the HR column RCC work.

A1 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
kitchen PF rcc work completed
Next we have planned plumbing work.

A2 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
kitchen PF rcc work completed.
Next we have planned plumb...  more