1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc comp... more1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
A1 FLAT
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
A2 FLAT.
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
A3 FLAT
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Next we have planned putty work.
Next we have planned shelf work.
C1 FLAT:
Inner plastering work completed.
Inner wall plumbing work completed.
toilet water proofing work completed
kitchen pf rcc completed.
Dead motor chipping work in progress.
Inner wall and ceiling 1st coat putty work in progress.
Next we have planned shelf work.
C2 FLAT:
Inner plastering work completed.
Inner wall plumbing work completed.
toilet water proofing work completed.
kitchen pf rcc completed.
Dead motor chipping work in progress.
Inner wall and ceiling 1st coat putty work completed.
Next we have planned tiles work.
COMMON:
common area plastering completed.
Terrace LMR bottom RCC Work completed.
terrace H/R and LMR slab steel fabrication work in completed.
Next we have H/R and LMR slab rcc work.
carparking plastering work completed.
OUTER:
Outer plastering work completed.
Outer plumbing work in progress.
Elevation Civil work completed.