1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
A1 FLAT
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we ... more1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
A1 FLAT
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
A2 FLAT.
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
A3 FLAT
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
Next we have planned putty work.
C1 FLAT:
Inner plastering work completed.
Inner wall plumbing work completed.
toilet water proofing work completed
kitchen pf rcc completed.
Next we have planned putty work.
C2 FLAT:
Inner plastering work completed.
Inner wall plumbing work completed.
toilet water proofing work completed.
kitchen pf rcc completed.
Next we have planned putty work.
COMMON:
common area plastering completed.
Terrace LMR bottom RCC Work completed.
terrace H/R wall brick work progress.
carparking plastering work completed.
OUTER:
Outer plastering work in progress.
Outer plumbing work in progress.
Elevation electrical work in progress.