STRUCTURE:
3rd floor RCC work is completed.
Next, we have planned to start the HR column RCC work.
A1 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
kitchen PF rcc work compled
Next we have planned plumbing work.
A2 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
kitchen PF rcc work completed.
Next we have planned plumbi... moreSTRUCTURE:
3rd floor RCC work is completed.
Next, we have planned to start the HR column RCC work.
A1 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
kitchen PF rcc work compled
Next we have planned plumbing work.
A2 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
kitchen PF rcc work completed.
Next we have planned plumbing work.
A3 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
kitchen PF rcc work completed
Next we have planned plumbing work.
B1 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
Next we have planned plumbing work.
B2 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
Next we have planned plumbing work.
B3 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
Next we have planned plumbing work.
B4 FLAT:
Roof level brick work completed.
inner Electrical conduit pipe fixing work completed
Inner wall plastering work completed.
Next we have planned plumbing work.
C1 FLAT:
Roof level brick work completed.
next we have planned electrical work
next we have planned inner plastering work.
C2 FLAT:
Roof level brick work completed.
next we have planned electrical work.
next we have planned inner plastering work.
C3 FLAT:
Roof level brick work completed.
Inner electrical- wall chasing work in progress.
next we have planned inner plastering work.