B1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
A1 FLAT
Inner plastering work completed.
inner plumbing and water proofing work in progress
kitchen pf rcc completed.
A2 FLAT.
Inner plastering work completed.
inner plumbing and water proofing work i... moreB1 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
B2 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
B3 FLAT:
Inner plastering work completed.
inner plumbing completed.
kitchen pf rcc completed.
A1 FLAT
Inner plastering work completed.
inner plumbing and water proofing work in progress
kitchen pf rcc completed.
A2 FLAT.
Inner plastering work completed.
inner plumbing and water proofing work in progress
kitchen pf rcc completed.
A3 FLAT
Inner plastering work completed.
inner plumbing and water proofing work in progress
kitchen pf rcc completed.
C1 FLAT:
Inner plastering work completed.
Inner wall plumbing work completed.
toilet water proofing work completed
kitchen pf rcc completed.
Next we have planned putty work.
C2 FLAT:
Inner plastering work completed.
Inner wall plumbing work completed.
toilet water proofing work completed.
kitchen pf rcc completed.
Next we have planned putty work.
COMMON:
common area plastering completed.
Terrace LMR bottom RCC Work completed.
terrace H/R Column steel fabrication work in progress.
carparking ceiling plastering work progress.
OUTER:
Outer plastering work in progress.
Outer plumbing work in progress.